The Maasvlakte 2 (MV2) case is selected to serve as hind castan example ex-post of possible adaptive monitoring schemes, i.e. how could adaptive executionmonitoring have helpedhad added value?

For the entire life spanlifespan of the Mainport Rotterdam, extensive Monitoring and Evaluation plans (MEPMEPs) have been set up, such as the MEP sand extractionSand Extraction and the MEP land reclamationLand Reclamation. Their goal is twofold: first is(1) verification of how do the actual effects relate toof the activity considered compare with the expected scenario'sscenarios, and second is(2) gathering data for filling the gaps inimportant knowledge gaps. Every five years, the monitoring plansall MEPs are evaluated. If needed, the management plans will be and adjusted if necessary. As the scopepart of the case studied isstudy marine sand mining, this historic case description of the Maasvlakte 2 focuses on the MEP sand extractionSand Extraction.

In the section "Lessons Learned" the Frame of Reference has been applied to the case study MV2. Note that the scope of this case study is limited to the construction phase of the MV2 and only considers the monitoring related to sand extraction.

    General Project Description

     

    Title: Monitoring of sand extraction areas for the Maasvlakte 2 extension

    Location: the Netherlands, Rotterdam port area

    Date: 2008 – 2013 (first phase) / 2033 (complete project)

    Partners: Maasvlakte 2 is part of the Rotterdam Project for Mainport Development (PMR). The contracting consortium PUMA (Projectorganisatie Uitvoering Maasvlakte 2) is responsible for the construction of Maasvlakte 2. PUMA is a partnership between Boskalis and Van Oord. Partners involved in the monitoring are: IMARES Wageningen UR; PUMA; Deltares; the Monitoring Taskforce of the Netherlands Institute of Ecology (now NIOZ); the Institute of Estuarine and Coastal Studies (IECS) at University of Hull; the Netherlands Organization for Applied Scientific Research (TNO); Rijkswaterstaat Dienst Noordzee.

    Costs: The costs of the Maasvlakte 2 project for the first construction phase amount to € 3 billion

    Abstract: The Maasvlakte 2 is a new location for port activities and industry to be created in the North Sea, for which 325 million m³ of sand is required that will be mainly extracted from the North Sea bed. As required under the permit conditions, monitoring plans have been set up, one of which - the MEP Sand Extraction - is evaluated in the study reported herein. The case description is based on the relevant BwN report (Tamis & Baptist, 2011).

    Topics: The phase 1 monitoring plan of sand extraction is the topic of this case study, with special focus on the perspectives offered by adaptive strategies.

    Project Objective

    The objective of the monitoring plan is verification of the predicted scenarios and filling knowledge gaps on nature, fish stocks and morphology.

    Project Solution

    Van Zanten et al., (2008) formulated a monitoring plan with the aim to verify the expected scenarios and fill the most important knowledge gaps. The monitoring plan, presented in the figure, follows the adaptive execution cycle: Every five years, the monitoring plans are evaluated. If needed, the management plans will be adjusted (more in Dutch).

    Adaptive strategies

    Considering adaptive monitoring strategies, there are two types of evaluation that can be distinguished: structural evaluation of the complete monitoring plan (every five years) and evaluation of results within certain themes. A separate working group has been established to conduct the monitoring program (van Zanten et al., 2008). Thus it is possible to maintain an adequate information exchange with the authorities and the initiator (Mainport Rotterdam).

    Periodic meetings are foreseen to discuss progress and results. Suggestions for adaptation of the monitoring plan can also be discussed at these sessions, e.g. to adjust the monitoring frequency, or to conducting additional measurements.

    Based on the baseline monitoring results, adaptations of the initial monitoring plan have already been made for some elements:

    Total suspended matter (TSM):

    • The number of sampling locations has been reduced, because a link between TSM and juvenile fish could not be observed and spatial correlation showed a redundancy of locations; the number of locations could therefore be decreased from 100 to 50.
    • The number of samples taken at each location has been increased, because temporal correlation was found to be only relevant in combination with more frequent sampling. The number of samples taken at each location has therefore been increased from 3 times (at 100 locations) in 2007 to 6 times (at 50 locations) in 2009.

    Benthos:

    • Benthos was monitored to determine the effect of increased TSM. Location and size of the benthos baseline monitoring area in 2006 have been changed, because of new insights into the TSM distribution; the second benthos baseline (2008) was adjusted to the TSM distribution (van Zanten et al., 2008).

    Juvenile fish:

    • Monitoring of this aspect has ended, because no relationship between TSM concentration and juvenile fish could be determined.

    Governance context

    Important governance observations from this case study are:

    • The authorities were open to new suggestions considering monitoring and allowed deviations from the initial permit requirements.
    • Adequate information exchange between the authorities and the initiator is crucial.

    Planning and Design

    Governance

    Monitoring is as a condition for permitting under several laws. The permit conditions include requirements for a monitoring plan, its execution and its evaluation. The main monitoring requirements in the case of sand extraction originate from:

    • the Nature Law, under authority of the Ministry of Economic Affairs, Agriculture and Innovation (Ministerie van Economische Zaken, Landbouw en Innovatie (EL&I)) and;
    • the Mineral Extraction Law, under authority of the Dutch Ministry of Infrastructure and the Environment (Ministerie van Infrastructuur en Milieu (I&M)).

    Monitoring plan

    The MEPs for Mainport Rotterdam have a twofold goal:

    • verification of the extent to which predicted scenarios of environmental effects correspond with reality;
    • gathering data for filling the most important knowledge gaps, as identified by the MER (Milieu Effect Rapport: Environmental Impact Assessment) and Passende Beoordeling (Appropriate Assessment for Natura2000) (van Zanten et al., 2008).

    The most important effects of large-scale sand extraction from the North Sea bed are thought to be the destruction of benthos followed by a recolonisation of the seafloor by benthos at the extraction site and its direct surroundings. Furthermore, there are potential effects of dredging-induced turbidity on the natural processes within the food chain and on the abundance of shellfish and birds. The MEP Sand Extraction is conducted by the Project organization Maasvlakte 2.

    The themes of the MEP Sand Extraction and the corresponding monitoring elements are listed below. A more detailed description can be found in the report on this study (Tamis & Baptist, 2011).

    Nature Law requirements

    Compliance monitoring is conducted as part of the permit conditions required by the Nature Law under the authority of the Ministry of EL&I. These requirements differ per protected area:

    • Voordelta
      • Land use (area)
      • Erosion induced by MV2
      • Change of the tidal wave
      • Increased total suspended matter (TSM)
      • Noise, ship movements and light emissions
    • Kwade Hoek
      • Deposition of nutrients (N) in the dunes
    • Haringvliet/Grevelingen/Eastern Scheldt
      • Effects of increased suspended matter on terns, monitored via TSM measurements.
    • Waddensea en North Sea coastal zone
      • TSM concentrations along the Zeeland and Holland coast, by use of modeling, remote sensing and field measurements.

    Mineral Extraction Law requirements

    • Bathymetry and extracted material
    • Seafloor properties
    • Suspended matter and changes in spring bloom
    • Species composition on the extraction sites
    • Sound

    Monitoring reports

    Both the Ministry of EL&I (Nature Law) and the Ministry of I&M (Mineral Extraction Law) demand periodic reports.

    All monitoring results shall be validated, analysed and reported by Mainport Rotterdam. The results and findings of all measurements completed in one year shall be summarized in an integrated annual report to be submitted to the authorities. This report includes at least an overview of the monitoring efforts, a description of the findings and the conclusion from the analysis and interpretation of results. The results will be compared with the predictions underlying the EIA (Ministry of I&M).

    The exact format of the annual reports and the format and frequency of possible interim sub-reports shall be established per monitoring theme in consultation with the authorities. The Mineral Extraction Law requires 6-monthly reporting. Extraction progress shall be reported each month, including the amount of material extracted, location and time of each extraction and the results of granulometric analyses (Ministry of I&M).

    The permit under the Nature Law states that each year before the 15th of July the results of the monitoring shall be submitted to the Ministry of EL&I. If necessary, interim reporting can be required (van Zanten et al., 2008).

    Construction

    Baseline monitoring

    In April 2006 the first baseline monitoring study started (Vertegaal et al. 2007). Baseline studies have been conducted for all elements of the monitoring plan (see monitoring plan in the Planning and Design phase of this case).

    Adaptive monitoring strategies in the monitoring plan of MV2

    The extensive monitoring program of MV2 already includes several adaptive strategies, as discussed below. The adaptations are, however, related to the monitoring itself, rather than to the extraction operations.

    The construction of Maasvlakte 2 is a huge project conducted over many years. The complete project is to be finalised in 2033. The first construction phase, from 2008 to 2013, requires 240 million m³ of sand. The current MEP (van Zanten et al., 2008) focuses on this first phase of the project, because the main effects are expected in this phase. For the second phase (after 2013), the MEP will be updated based on results from phase 1, including the lessons learned. Before implementation of the new MEP, it will be submitted to the authorities for approval.

    Considering adaptive monitoring strategies, there are two types of evaluation that can be distinguished: structural evaluation of the entire MEP and evaluation of results within themes.

    Structural evaluation of the entire MEP

    According to the website of the MV2 project (accessed on January 29, 2010), the MEPs are evaluated every five years and, if needed, plans will be adjusted. The set-up of the MEP (van Zanten et al., 2008), however, does not refer to such a structural evaluation of the entire MEP: it includes only a periodic evaluation of monitoring plans per theme. The establishment of a separate working group for the monitoring program within the Project Organisation Maasvlakte 2 (van Zanten et al., 2008) makes it possible to maintain an adequate information exchange between the authorities and the initiator. According to the MEP it is preferable to discuss monitoring progress and results at periodic meetings. Suggestions for adaptation of the monitoring program can be discussed there, such as adjusting the monitoring frequency or conducting additional measurements.

    Other relevant documents, such as the EIA (Vertegaal et al., 2007) and the conditions of the extraction permit (Ministerie van Verkeer en Waterstaat, 2007), do not mention a structural evaluation of the entire MEP.

    Evaluation of monitoring plans per theme

    Two basic conditions in the MEP enable adaptation of the monitoring program:

    • The evaluation of the monitoring plan after new results have been analysed;
    • The opportunity to discuss the monitoring program with the authorities and, if necessary and approved, to adjust it.

    Monitoring themes as required by the Ministry of EL&I

    The monitoring as required by the Ministry of EL&I (Nature law) focuses on the abiotic effects (van Zanten et al., 2008). As long as these effects remain below the limits set in the Appropriate Assessment (Dutch: Passende Beoordeling), the same is assumed for the biotic effects. As potential biotic effects will be caused by changes in abiotic conditions and "worst case" assessments of these effects, this assumption is considered to be justified. According to condition 27 of the Nature Law Permit, additional monitoring shall be considered whenever monitoring results show that the (abiotic) effect is larger than expected or when there is an indication that this might occur (van Zanten et al., 2008).

    Monitoring themes as required by the Ministry of I&M

    According to the permit conditions, the monitoring plan shall include for each theme a motivation of the parameters to be monitored, at what locations and with what frequency. Also, criteria shall be given for adaption of or deviation from these definitions and possible measures shall be identified in case environmental effects threaten to exceed the set limits, based on e.g. the impact-response chains as described in the EIA (Ministerie van Verkeer en Waterstaat, 2007). Monitoring is planned in periods in which effects are expected, the monitoring frequency is chosen such, that the data gathered will provide sufficient insight into the relevant effects. In consultation with the authorities responsible (i.e. the Ministry of I&M) and with their approval, the monitoring frequency will be adjusted if the analyses of the monitoring give cause for it (van Zanten et al., 2008).

    The monitoring program is set up in such a way, that statistical analyses can detect changes in tidal currents, wave height and water depth. Variations of the monitoring results through 
    the tidal cycle can thus be compensated, for instance, and correlations between measured parameters can be determined (Vertegaal et al., 2007).

    The criteria for adaption/deviation of the monitoring plan per theme, as included in the MEP, are presented in the table below. Further details can be found in Tamis & Baptist (2011).

    Operation and Maintenance

    Delivered project

    Because this case description is focused on monitoring of the sand extraction for Maasvlakte 2, 'post-construction' refers to the monitoring phase after the sand extraction has ended.

    Strategies

    The government initially required yearly measurements during the first five years after extraction had ended, and subsequently every five years until no more changes are observed. The actual monitoring plan deviates from this requirement: it suggests to choose an adaptable frequency that enables an adequate description of the developments within the area and to show whether effects have vanished. The monitoring frequency can be adapted in agreement with the authorities (van Zanten et al., 2008).

    Execution

    The sand extraction for the Maasvlakte 2 is part of the 1st phase construction, which ends in 2013. The monitoring after sand extraction has ended is therefore expected to start in 2013.

    Lessons Learned

    Objectives

    To identify the lessons learned from the monitoring of the Maasvlakte 2 extension, the Frame of Reference (Van Koningsveld, 2003) is applied to the monitoring plan of MV2. The Frame of Reference tool can be used to support decision making, as well as to set a target for expertise improvement. The main research question is in how far the monitoring program uses adaptive management approaches as set by the Frame of Reference.

    The Strategic Objective is: verification of the predicted scenarios and identifying important discrepancies and knowledge gaps in the fields of nature, fish stocks and morphology.
    In general, the Evaluation Procedure is threefold:

    1. are the observed effects as predicted?
    2. if not, can this be explained from existing knowledge?
    3. If not, what are the most important knowledge gaps and how can they be filled?

    The Operational Objectives and other elements of the Frame of Reference are described in Tamis & Baptist (2011). In the monitoring plan the operational objectives are described adequately, as well as the quantitative state concept (how to describe the state of the system) and the benchmarking desired state. What is missing in the monitoring plan is the intervention procedure (how to manipulate (part of) the system in order to bring it to the desired state).

    Lessons

    Evaluation of the MV2 monitoring program with regard to adaptive monitoring showed that:

    • Based on a thorough motivation, the initiating stakeholder was allowed by the authorities to deviate from the permit requirements in the monitoring program of MV2.
    • The extensive monitoring program of MV2 already included several adaptive strategies. The adaptations were, however, related to the monitoring itself, rather than the execution of extraction work.

    Applying the Frame of Reference to the MV2 monitoring program showed that:

    • Almost all elements of the 'basic' frame of reference can be found in the monitoring program of MV2, leading to a successful and coherent approach. The desired state is included for each element and, in combination with the evaluation procedure, enables adaptive monitoring.
    • The main ‘white spot’ is the lack of an intervention procedure which specifies what can be done to bring the system into a desired state.

    The MV2 monitoring program is a good example on how to meet the monitoring requirements as set by the authorities without unnecessary monitoring efforts.