The project activities have started.
A first demo of the map table was realized.
- A first draft project report has been delivered.
- Due to a delay of data delivery, the deadline of the project has been postponed.
- Internal demo for DairyNZ about the project.
- Setting up the hydrological model (WFLOW) and the connection with the WFD Explorer.
2015 Q3:
- Finalisation of the first version of the Delta Data Viewer (map table) application for the Waituna catchment, including measures and scenarios.
- Start of the activities to built the groundwater-surface water connection (WFLOW-MODFLOW).
2015 Q4:
- The project was presented at the Fresh Water Conference November 23-26, Wellington, New Zealand (see product 1).
2016 Q1:
2016 Q2:
Products:
- Poster presented at the Fresh Water Conference November 23-26, 2015