In October 2022 the team conducted a field testing campaign. A total of 27 tests have been carried out between rain gardens and permeable pavement facilities. The tests were done

Mapping of existing green infrastructure projects

...

The research and field test results are to be discussed and integrated in a final stakeholder workshop on green infrastructure in New Orleans.

Documents

TopicLink to document
Green infrastructure as part of urban drainage

Report

Green infrastructure field tests

Report

ClimateScan: documentation of green infrastructure facilities and test results

Interactive website

Mapping of existing green infrastructure projects
Workshop optimization of green infrastructure(Workshop slides will be made available later)