Iteration 1 : SDK and testing the main concepts

Starts: After the Trento OATC meeting (January 16th 2009)
Ends: Before the Wallingford OATC meeting (March 9th 2009)
Tasks:

  • Implement OATC.OpenMI.Sdk.Backbone
    Implement OATC.OpenMI.Sdk.Backbone.UnitTest
    Deadline: January 28th 2009
    Responsible: Stef
  • Implement OpenMI.Standard Java interfaces
    Deadline: January 28th 2009
    Responsible: Stef
  • Implement Oatc.OpenMI.Sdk.Buffer
    Implement OATC.OpenMI.Sdk.Buffer.UnitTest
    Deadline: February 3rd 2009
    Responsible: Stef
  • Implement Oatc.OpenMI.Sdk.Spatial
    Implement OATC.OpenMI.Sdk.Spatial.UnitTest
    Deadline: February 12th 2009
    Responsible: Jan
  • Implement OATC.OpenMI.Sdk.Wrapper
    Implement OATC.OpenMI.Sdk.Wrapper.UnitTest
    Deadline: February 12th 2009
    Responsible: Jan
  • Test against the 7 component types (see section 3.1)
    Simple unit test, that will be published on the wiki.
    Deadline: March 1st 2009
    Responsible: Gena
Iteration 2: Configuration editor and further refinements

Starts: After the Wallingford OATC meeting (March 13th 2009)
Ends: Before the DHI OATC meeting (April 21st 2009).
Tasks:

  • Implement OATC.OpenMI.GUI.Controls
    Implement OATC.OpenMI.GUI.ConfigurationEditor
    Implement OATC.OpenMI.GUI.Core
    Deadline: April 21st 2009
    Responsible: Adrian
  • Documentation
    In-source comment in the OpenMI.Standard
    Document explaining the main concepts including sequence diagrams
    Deadline: April 21st 2009
    Responsible: To be decided on the Wallingford OATC meeting
  • Target: To get everything to a state where we can start working with real components.
Iteration 3: Migration of commercial models and documentation

Starts: After the DHI AOTC meeting (April 24th 2009)
Ends: Before the Delft OATC meeting (June 9th 2009)
Tasks:

  • Migration of Mike 11 and Mike She
    Deadline: June 9th 2009
    Responsible: Jan
  • Migration of HydroWorks RS and CS
    Deadline: June 9th 2009
    Responsible: Adrian
  • Documentation, migration of the HowTo wiki pages to version 2
    Deadline: June 9th 2009
    responsible: To be decided on the DHI OATC meeting

*Target: To test usability and performance of version 2 for real models.

Iteration 4 : External review and further migration of models

Starts: June 12th 2009-01-21
Ends: October 13th 2009
Tasks:

  • Migration of Delft3D and Sobek
    Deadline October 13th 2009
    Responsible: Stef
  • Assist external reviewers
Iteration 5: Adjustments according to comments from reviewers

Starts: October 14th 2009
Ends: December 19th 2009
Tasks

  • Update the standard, SDK, GUI, and documentation according the comments provided by the reviewers and the OAEC
    Deadline December 19th
    Responsible: OATC
  • Submit the standard release to the OAEC
    Deadline: December 20th 2009
    Responsible: OATC