Iteration 1 : SDK and testing the main concepts
- Starts: After the Trento OATC meeting (January 16th 2009)
- Ends: Before the Wallingford OATC meeting (March 9th 2009)
- Tasks:
- Implement OATC.OpenMI.Sdk.Backbone
Implement OATC.OpenMI.Sdk.Backbone.UnitTest
Deadline: January 28th 2009
Responsible: Stef
- Implement OATC.OpenMI.Sdk.Backbone
-
- Implement OpenMI.Standard Java interfaces
Deadline: January 28th 2009
Responsible: Stef
- Implement OpenMI.Standard Java interfaces
-
- Implement Oatc.OpenMI.Sdk.Buffer
Implement OATC.OpenMI.Sdk.Buffer.UnitTest
Deadline: February 3rd 2009
Responsible: Stef
- Implement Oatc.OpenMI.Sdk.Buffer
-
- Implement Oatc.OpenMI.Sdk.Spatial
Implement OATC.OpenMI.Sdk.Spatial.UnitTest
Deadline: February 12th 2009
Responsible: Jan
- Implement Oatc.OpenMI.Sdk.Spatial
-
- Implement OATC.OpenMI.Sdk.Wrapper
Implement OATC.OpenMI.Sdk.Wrapper.UnitTest
Deadline: February 12th 2009
Responsible: Jan
- Implement OATC.OpenMI.Sdk.Wrapper
-
- Test against the 7 component types (see section 3.1)
Simple unit test, that will be published on the wiki.
Deadline: March 1st 2009
Responsible: Gena
- Test against the 7 component types (see section 3.1)
Iteration 2: Configuration editor and further refinements
- Starts: After the Wallingford OATC meeting (March 13th 2009)
- Ends: Before the DHI OATC meeting (April 21st 2009).
- Tasks:
- Implement OATC.OpenMI.GUI.Controls
Implement OATC.OpenMI.GUI.ConfigurationEditor
Implement OATC.OpenMI.GUI.Core
Deadline: April 21st 2009
Responsible: Adrian
- Implement OATC.OpenMI.GUI.Controls
-
- Documentation
In-source comment in the OpenMI.Standard
Document explaining the main concepts including sequence diagrams
Deadline: April 21st 2009
Responsible: To be decided on the Wallingford OATC meeting
- Documentation
- Target: To get everything to a state where we can start working with real components.
Iteration 3: Migration of commercial models and documentation
- Starts: After the DHI AOTC meeting (April 24th 2009)
- Ends: Before the Delft OATC meeting (June 9th 2009)
- Tasks:
- Migration of Mike 11 and Mike She
Deadline: June 9th 2009
Responsible: Jan
- Migration of Mike 11 and Mike She
-
- Migration of HydroWorks RS and CS
Deadline: June 9th 2009
Responsible: Adrian
- Migration of HydroWorks RS and CS
-
- Documentation, migration of the HowTo wiki pages to version 2
Deadline: June 9th 2009
responsible: To be decided on the DHI OATC meeting
- Documentation, migration of the HowTo wiki pages to version 2
*Target: To test usability and performance of version 2 for real models.
Iteration 4 : External review and further migration of models
- Starts: June 12th 2009-01-21
- Ends: October 13th 2009
- Tasks:
- Migration of Delft3D and Sobek
Deadline October 13th 2009
Responsible: Stef
- Migration of Delft3D and Sobek
-
- Assist external reviewers
Iteration 5: Adjustments according to comments from reviewers
- Starts: October 14th 2009
- Ends: December 19th 2009
- Tasks
- Update the standard, SDK, GUI, and documentation according the comments provided by the reviewers and the OAEC
Deadline December 19th
Responsible: OATC
- Update the standard, SDK, GUI, and documentation according the comments provided by the reviewers and the OAEC
-
- Submit the standard release to the OAEC
Deadline: December 20th 2009
Responsible: OATC
- Submit the standard release to the OAEC