Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

To run all preceding tasks, including re-running those tasks already up to date, select the Run all to Selected option. This will run all tasks that have not yet been run in the defined sequence.

Running the group workflow on the server

Once the iteration of tasks has been completed, the workflow associated with the group selected can be submitted for running on the server. In effect this is the same as submitting that task through the Manual Forecast Dialogue. This workflow will, however, use the properties as defined for the sub-tasks when running these locally.

Showing results of a sub-task

To view the results of a sub task, the option Show Results... can be selected. This opens the time series display, and opens the pre-configured display that has been configured to be associated with that sub-task.

Setting the properties of task runs

The properties of the task runs can be amended from the default settings by selecting the Properties option.

Through this display the properties of the run can be specified. This display is similar to the options available in the Manual Forecast Dialogue

A what-if scenario can be selected to be used in the task runs

The run can be set to use to cold state start by selecting the Cold State option and setting number of days prior to the Forecast T0 that the run should start.

The run can be set to use a warm state by selecting the state search period. This can be set relative to the Forecast T0 by using the Warm State option. Alternatively the historical run to start from can be selected in the list of dates available in the Warm State Selection option.

The forecast length can be specified to deviate from the default by selecting the option Forecast Length and entering the appropriate number of days.

One the options have been defined, these will be used for all tasks run within the active session of the interactive forecast display.

Image Added

Configuration of the Interactive Forecast Display

The interactive forecast display is an implementation of the TaskRun dialogue.

This is the configuration of a display and can be found in the displayConfigFiles section of the configuration.

The configuration of the display requires a layout of the flow chart to be defined, as well as the workflows associated to each group of tasks, and sub-tasks.